Last updated on : 15/05/2013
      Home
      Web Information Manager contact details
      What's New
      About Us
      Beneficiaries under NEC Scheme Financial Support to Students of NER
      NERLP - A World Bank Project
      NEC Schemes Upto End of the 10th Plan Period
      Information Required under RTI Act 2005
      Release of Funds
      Monthly Progress Report
      Guidelines Rules and Forms
      Papers and Documents
      Tenders and EOI
      NEC Library Book Search
      Press Releases and Noteworthy News Items
      Advertisements and Tender
      Immovable Property Statements of Group A Officers
      Photo Gallery
      North Eastern States
      NEC Supported Institutions
      Other Important Sites
      Send Feedback
Doyang Hydro Electric Project -75 MW

1. Name of the project - Doyang Hydro Electric Project (75 MW).

2. Name of the Implementing Agency - North Eastern Electric Power Corporation (NEEPCO)

3. Status - Completed

4. Amount released (Rs in lakh) :

Doyang Fund Released
By NEC Financial Institutions
Total Equity Govt. Loan LIC Loan PFC Loan Bond
75870.40 19237.45 30748.04 8100.00 5085.00 12700.00

5. Brief note on the project - Doyang Hydro Electric Project in Nagaland was originally approved by the MHA at an estimated cost of Rs.166.66 crores (at February, 1988 price level) under the NEC Plan, in July, 1989. This project was taken up for implementation in July 1989 by NEEPCO. The time-frame for completion of the project was stipulated for 5 years and 1 month i.e. the project, as per the original schedule, was to be completed by August 1994. The installed capacity of the project is 3 X 25 MW = 75 MW.

All works are completed and units synchronized as below:-

Unit III - Synchronized on 29.06.2000

Unit IT - Synchronized on 05.07.2000

Unit I - Synchronized on 08.07.2000